Liongate provided baseline planning & scheduling services for an Irish MEP subcontractor company for an 12mw data center construction project in Copenhagen.

We worked with the client team and used our expertise to create the most efficient and achievable programme for them.

.

  • Project Name: CPH Data Center Project
  • End Client: Microsoft
  • Client: Irish MEP subcontractor, under NDA
  • Location: Copenhagen, Denmark
  • Project Size: 12 MW
  • Services Provided: Construction Programme Planning & Scheduling

services we provided

baseline programme

We created baseline programme by engaging all the team.

man-power loading

Man-power assessments done and programme manhours loaded.

activity coding

All programme activities coded. This enabled the Client to filter all different disciplines and subbies.